GOMESA Application Details


Internal Project Number
281422
1. Title of Project
Wolf River Channel Dredging
2. Location of Project
30deg21min21.4secN, 89deg17min27.4secW, 30deg20min53.9secN, 89deg17min56.4sec W
3. Requesting Organization
Harrison County
4a. Name
Jaclyn Turner
4b. Position
4c. Phone Number
228-832-4891
4d. Fax Number
4e. Address Line 1
12423 Seaway Road, Suite C
4e. Address Line 2
4e. City, State Zip
Gulfport, MS 39503
4f. Email
jmturner@co.harrison.ms.us
5. FundingRequested
$2,444,400
Awarded Amount:
6. Other State or Federal Funding Sources
No
7a. Amount of Additional Funds
7b. Source of Additional Funds
8. Total Project Funds Amount
$2,444,400
9. Project Description/Overview
The navigable channel at the mouth of the Wolf River has been silting in over time, and is in need of maintenance dredging, some debris removal, and restoration of channel markers. Jetty construction to protect the channel upstream of this location has shifted the location of siltation further into the bay, resulting in the need for dredging to maintain safe access to boaters from the Wolf River. Much of this area is currently only 1'-2' deep, causing a hazard to water traffic entering or leaving the Wolf River. This area does fall inside a federally permitted channel, helping with the permitting process. To provide safe navigation through this area, approximately 4,000 feet of the channel, approximately 100' wide, needs to be dredged an average of 4', resulting in a channel depth of -6'. A large tree stump/root ball near the location of channel marker 5 also needs to be removed, assumed to be left from a storm in recent years. Also requested is restoration of channel markers at location #3 and lighted channel markers at location #5.
10. Project Goals/Objectives
Provide save navigable channel between the bay and Wolf River. Remove sediment and debris from navigable channel. Restore channel markers along federally permitted channel.
11. Which of the following authorized uses set forth in the GOMESA Act does this project fall under?
(A) Projects and activities for the purpose of coastal protection, including conservation, coastal restoration, hurricane protection, and infrastructure directly affected by coastal wetlands losses
Yes: Migrating impact from coastal wetland losses impacts the sediment transport around navigable channels - maintenance and restoration is needed to provide access to the Wolf River.
(B) Mitigation of damage to fish, wildlife, or natural resources.
(C) Implementation of a federally-approved marine, coastal, or conservation management plan.
(D) Mitigation of the impact of Outer Continental Shelf activities through funding of onshore infrastructure projects.
Yes: Maintaining a safe navigation channel between the Gulf, Bay, and Wolf River mitigates the impact of Outer Continental Shelf activities.
12. Project Timetable/Milestones
3 months: Solicit and contract engineering, permitting consultant 6-12 months: Survey channel conditions, permit dredging operations, prepare plans and specifications for bidding project 3 months: Advertise, bid, award project 6-9 months: Complete construction effort, close project and grant
13. Project Timing
Short-term
14. Current status of architectural/engineering plans & specifications for this project (if applicable):
Other Ready to begin Funds Not Budgeted
15. In what way does this project meet the goals and objectives of the Department of Marine Resources, which includes enhancing, protecting and conserving the marine interest of Mississippi for present and future generations?
This project will enhance and protect the navigable waterway connecting the Gulf to Wolf River through the Bay. This provides water access to numerous points along all of the nearby water bodies, allowing for recreation, educational, and commercial boat traffic in the federally permitted channel safely.
16. Estimated Years To Completion
2
17. Estimated Completion Date
12/22/2028
Budget:
Salaries,Wages, Fringe
Travel
Architecture & Engineering
$415,900
Legal
Consulting
Construction
$2,028,500
Site Work
Equipment
Indirects
Other
Total
$2,444,400
Application Submission Date
08/26/2026
Fiscal Year
2028
Project Status
Application Status
Submitted
Meets Criteria
Internal Notes:
Attachments:
https://gomesa.dmr.ms.gov/attachments/GOMESA_1422_Attachment.pdf
Hyperlink:
Attachments
Back to List
An unhandled error has occurred. Reload 🗙