GOMESA Application Details


1. Title of Project
Long Beach Smallcraft Harbor - Southern Quay Bulkhead
2. Location of Project
Long Beach Smallcraft Harbor, on the southern quay, a small concrete paved area at the southern side of the Harbor. The quay provides a fishing & parking area for Harbor users and is currently in need of significant repairs.
3. Requesting Organization
City of Long Beach
4a. Name
George Bass
4b. Position
4c. Phone Number
2288631556
4d. Fax Number
4e. Address Line 1
P.O. Box 929
4e. Address Line 2
4e. City, State Zip
Long Beach, MS 39560
4f. Email
mayor@cityotlongbeachms.com
5. FundingRequested
$2,554,000
Awarded Amount:
$2,554,000
6. Other State or Federal Funding Sources
No
7a. Amount of Additional Funds
$0
7b. Source of Additional Funds
8. Total Project Funds Amount
$2,554,000
9. Project Description/Overview
This project is intended to construct improvements to the eastern boundary of the Long Beach Smallcraft Harbor. The improvements will be in the form of a vertical concrete wall/bulkhead at or near 10 feet above mean sea level, raising the existing structural protection in the area by nearly 4 feet. This increase in height of the structural protection will not only provide protection and stabilization at the referenced location, but additionally, to the remainder of the Harbor infrastructure, which is often damaged even by small storms which elevate waves and water above the elevation of the existing structural elements on-site Not only do these repetitive damages and the subsequent repairs cause significant economic damage to the City, but they additionally cause substantial impact to the operation and function of the Harbor, a critical public service in the City. Obviously, impacts to the operation of the Harbor causes additional economic harm to the City through the loss of slip rentals, fuel sales, etc. Furthermore, the damage which occurs during a storm generally includes large amounts of material washing into the parking area near the project area, and also material washing away into the MS Sound. A bulkhead wall will help ameliorate all these impacts.
10. Project Goals/Objectives
- Provide significant improvements to hurricane/storm resistance for the eastern border of the Harbor, which is an often-damaged area during storms. Hardening the eastern border of the Harbor will also provide protection for the Harbor basin piers, etc. - Mitigation of damages to ecological areas due to repeated damage and repair efforts in the area - Reduction in repetitive losses to marina infrastructure (piers, electrical systems, etc.) in the Harbor
11. Which of the following authorized uses set forth in the GOMESA Act does this project fall under?
(A) Projects and activities for the purpose of coastal protection, including conservation, coastal restoration, hurricane protection, and infrastructure directly affected by coastal wetlands losses
Yes: Improvements to the southern quay bulkhead along the eastern side of the Harbor marina which will stabilize that area against repetitive damages during storm events. By stabilizing and securing this area it will reduce the soil loss into the waters of the MS Sound.
(B) Mitigation of damage to fish, wildlife, or natural resources.
(C) Implementation of a federally-approved marine, coastal, or conservation management plan.
(D) Mitigation of the impact of Outer Continental Shelf activities through funding of onshore infrastructure projects.
Yes: Construction of this project will provide significant improvement to the eastern border of the Long Beach Smallcraft Harbor, stabilizing that area against repetitive damages during storm events. This area is an area often damaged by storms, but more importantly, by hardening & raising the eastern "shore" of the Harbor, there will be significant reduction in damages to the infrastructure inside the Harbor, such as the piers, launches, electrical systems, etc. By stabilizing and securing the area, the project will also have positive environmental impact by reducing the debris which is often washed back into the MS Sound after the damaging events which occur so often.
12. Project Timetable/Milestones
It is estimated that this project could be fully constructed within two (2) years from the date of funding. This allows one (1) year for permitting, design, and bidding, followed by one (1) year of construction.
13. Project Timing
Short-term
14. Current status of architectural/engineering plans & specifications for this project (if applicable):
In Progress Funds Budgeted
15. In what way does this project meet the goals and objectives of the Department of Marine Resources, which includes enhancing, protecting and conserving the marine interest of Mississippi for present and future generations?
By protecting and hardening the Long Beach Small Craft Harbor it will allow fisherman a safe place to store and launch their boats, as well as the citizens of the Long Beach and visitors to access and enjoy the harbor. These visitors of harbor will generate funding for coastal conservation programs.
16. Estimated Years To Completion
2
17. Estimated Completion Date
5/1/2025
Budget:
Salaries,Wages, Fringe
$0
Travel
$0
Architecture & Engineering
$474,000
Legal
$0
Consulting
$0
Construction
$2,080,000
Site Work
$0
Equipment
$0
Indirects
$0
Other
$0
Total
$2,554,000
Internal Project Number
2024024
Application Submission Date
07/01/2022
Fiscal Year
2024
Project Status
Awarded
Application Status
Accepted
Meets Criteria
Yes
Internal Notes:
1636-x
Back to List
An unhandled error has occurred. Reload 🗙