1. Title of Project
Harbor Repairs and Improvements
2. Location of Project
100 Jody Compretta Drive Bay St Louis, MS 39520
3. Requesting Organization
City of Bay St Louis
4a. Name
Mike Favre
4b. Position
4c. Phone Number
(228) 466-5490
4d. Fax Number
4e. Address Line 1
688 Highway 90
4e. Address Line 2
4e. City, State Zip
Bay St. Louis , MS
4f. Email
mfavre@baystlouis-ms.gov
5. FundingRequested
$1,200,000
Awarded Amount:
$0
6. Other State or Federal Funding Sources
No
7a. Amount of Additional Funds
$0
7b. Source of Additional Funds
8. Total Project Funds Amount
$1,200,000
9. Project Description/Overview
This City of Bay St. Louis is proposing a project that addresses the settlement of the harbor sidewalks, which has led to the sidewalk to become uneven. Due to the unevenness, this has resulted in safety risks and becoming non ADA compliant. The project includes demolition and excavation of the existing sidewalk and asphalt, followed by the installation of geofabric, new backfill, sand, and reconstruction of the sidewalk. These measures are intended to create a stable hurricane resistant infrastructure, and resolves an emergency situation by removing obstructions and hazards to pedestrian access to the harbor.
10. Project Goals/Objectives
- Hurricane Mitigation and Resilience - Safe Public Access
11. Which of the following authorized uses set forth in the GOMESA Act does this project fall under?
(A) Projects and activities for the purpose of coastal protection, including conservation, coastal restoration, hurricane protection, and infrastructure directly affected by coastal wetlands losses
Yes: This proposed project will provide hurricane mitigation and resilience by utilizing hurricane resistant materials for long term stability of the Harbor infrastructure.
(B) Mitigation of damage to fish, wildlife, or natural resources.
(C) Implementation of a federally-approved marine, coastal, or conservation management plan.
(D) Mitigation of the impact of Outer Continental Shelf activities through funding of onshore infrastructure projects.
12. Project Timetable/Milestones
Design and Planning - 3 months Construction - 6 months Closeout - 1 month
13. Project Timing
Short-term
14. Current status of architectural/engineering plans & specifications for this project (if applicable):
In Progress Funds Not Budgeted
15. In what way does this project meet the goals and objectives of the Department of Marine Resources, which includes enhancing, protecting and conserving the marine interest of Mississippi for present and future generations?
This proposed project provides safe area for pedestrians to access coastal waters for fishing activities thus preventing future damage to existing natural resources. This sidewalk project will be reconstructed to withstand hurricane forces allowing many generations to experience the Bay St. Louis Harbor.
16. Estimated Years To Completion
1
17. Estimated Completion Date
1/31/2026
Budget:
Salaries,Wages, Fringe
$0
Travel
$0
Architecture & Engineering
$120,000
Legal
$0
Consulting
$0
Construction
$1,080,000
Site Work
$0
Equipment
$0
Indirects
$0
Other
$0
Total
$1,200,000
Internal Project Number
1285
Application Submission Date
06/19/2024
Fiscal Year
2026
Project Status
Application Status
Submitted
Meets Criteria
Internal Notes:
Back to List
An unhandled error has occurred. Reload 🗙